Skip to Main Content

Insight

September 12, 2025
Air Quality Update

EPA Broadens Pre-Construction Activities Under New Source Review Permitting

On September 9, 2025, EPA announced new guidance on New Source Review (NSR) pre-construction permitting requirements that broadens the types of activities that can be undertaken prior to obtaining an air permit. The guidance gives permittees flexibility to begin initial construction activities such as pouring pads and constructing building shells—speeding up construction timelines on time-sensitive projects such as semiconductor manufacturers, data centers, and energy projects.  

An owner or operator of a facility cannot “begin actual construction” under existing NSR regulations until an air quality permit has been issued; this term is defined as the “initiation of physical on-site construction activities on an emissions unit which are of a permanent nature,” including building supports, foundations, and pipework. Consistent with 2020 draft EPA guidance that was never finalized, EPA is revising its interpretation of the term “begin actual construction” to allow for initiation of on-site construction on those parts of a facility that are not emissions units.  The guidance applies this interpretation to authorize TSMC Arizona Corporation to pour foundations and begin constructing the core and shell of a semiconductor manufacturing plant that eventually will house emissions units as long as they do not begin construction on any equipment that could be classified as an emissions unit.  This approach runs contrary to historic EPA interpretations, under which sources were limited to ordering equipment, site clearing and grading, and temporary storage of equipment and materials.  

According to EPA’s announcement, the Agency plans to propose and finalize its revisions to NSR regulations, including the definition of “begin actual construction,” in 2026. Until that process is completed, EPA “may advise on these matters on a case-by-case basis” and will interpret the pre-construction requirements under NSR to narrowly focus on those parts of a facility that qualify as an “emissions unit,” and will allow other physical on-site construction to commence without a permit. 


This publication is designed to provide general information on pertinent legal topics. The statements made are provided for educational purposes only. They do not constitute legal or financial advice nor do they necessarily reflect the views of Holland & Hart LLP or any of its attorneys other than the author(s). This publication is not intended to create an attorney-client relationship between you and Holland & Hart LLP. Substantive changes in the law subsequent to the date of this publication might affect the analysis or commentary. Similarly, the analysis may differ depending on the jurisdiction or circumstances. If you have specific questions as to the application of the law to your activities, you should seek the advice of your legal counsel.

DISCLAIMER

Unless you are a current client of Holland & Hart LLP, please do not send any confidential information by email. If you are not a current client and send an email to an individual at Holland & Hart LLP, you acknowledge that we have no obligation to maintain the confidentiality of any information you submit to us, unless we have already agreed to represent you or we later agree to do so. Thus, we may represent a party adverse to you, even if the information you submit to us could be used against you in a matter, and even if you submitted it in a good faith effort to retain us.